Westnor Apartments Kitchen Lighting Replacement Schedule

Remodel
This work is to include replacing the exiting fluorescent kitchen light with a surface LED type in 89 living units in the three-story apartment building.

Status

Accepting Bids

Bid Date 12/3/24 9:00am

Company & Contacts

Fond du Lac Housing Authority
Dave Schulze  
920-894-4710

Location

653 West Arndt Street, Fond du Lac WI 54935.

NOTES from MSA Professional Services Inc.

  • Advertise for bidding – Sunday, November 17, and November 24, 2024

  • Project out to bidders – Monday, November 18, 2024

  • Pre-bid walk thru – There will be no pre-bid walk thru

  • Bids Due – Tuesday (9:00 am), December 3, 2024

  • Board ready – Wednesday, December 4, 2024, for approval of bids Board meets (second Monday) December 9, 2024

  • Award contract December 10, 2024

  • Start project December 11, 2024.

  • Substantial completion April 18, 2025

  • Final completion April 25, 2025


It is the bidder’s sole responsibility to review the “Addenda” tab during the bidding process for new postings!

The Owner, Architect, General Contractor, Printer, or PlanRoom will not be responsible for bids or sub-bids based on single drawings, specification sheets or observation or use of partial sets of documents. It is the bidder’s sole responsibility to review & understand all project requirements prior to submitting a bid!